Pier 27 Construction Overview for the week of March 18

Pier 27 Construction Overview for the week of March 18

Phase 3 Construction overview This week the focus of work on the top of the Phase 3 Tower will be prepping, forming and pouring columns and walls from the 30th to the 31st floor.  We expect the 31st floor slab to be poured on Monday, March 25th. If the schedule for...

Wednesday Update + 3 day look ahead as of March 13, 2019

3 Day look ahead for Pier 27 Phase 3 The 30th floor slab concrete pour remains on schedule for Friday March 15. Work will run from the morning through the evening to complete the pour and the accompanying concrete finishing.  The raising of the hoist (external...

Pier 27 construction outlook week of March 11, 2019

Phase 3 overview As of today, the next major concrete pour for the 30th floor is scheduled for this coming Friday, March 15th. As with previous major slab concrete pours it is expected to run throughout the day, with concrete finishing running into the evening. As the...

Wednesday Update + 4-day look ahead as of March 6, 2019

4-day Lookahead at Pier 27 Phase 3 Construction highlights in the coming 4 days:Crews will continue to raise the hoist: the external elevator for Phase 3. There will be concrete pours on Friday for walls and columns from the 29th to 30th floors.Installing railings on...

Update for Wednesday, March 6, 2019

Mechanical Room Work – UPDATED The in the work in the 29 Queens Quay Mechanical that was scheduled for Tuesday, has  now been rescheduled to Wednesday, March 6. Workers will be on-site to drill a core to connect the fire alarm systems from the 29 Queens Quay...

Look ahead to the week of March 4th, 2019

UPDATED: Construction Outlook for the week of March 4 29th Floor Concrete PourThe next slab concrete pour will begin at 7:30 am on Monday, March 4 for the 29th floor. Concrete pouring will be completed in the afternoon. Concrete finishing will continue through the...

Mid-week update for Pier 27

Wednesday Feb 27 recap Given the snowstorm today, February 27, concrete work as suspended. Drywall, electrical work, floor levelling and framing  continued in the podium and lower tower levels.  Work for the balance of the week With mostly clear skies forecast for...

UPDATED: Saturday work & look ahead to the week of Feb 25, 2019

UPDATED: for the Week of February 25, 2019 A key focus at the beginning of the week will be preparing for the next major slab concrete pour, which has now been rescheduled for Monday, March 4, as a result of  the delay caused by the  snow storm on Wednesday, February...

Construction Update: Wednesday February 20, 2019

Thursday Electrical Room Work 29 Queens Quay E. Tomorrow, Thursday, February 21, from 7:00 AM to 2:00 PM,  TMG’s electricians will be accessing 29 Queens Quay, Parking Level 4 (P4), Generator Room.  The generator is shared between Phase 3 building and 29 Queens...

Week recap, Saturday construction & Look Ahead, February 16/19 +

Recap for the week of Feb 11 – 15, 2019 This past week, February 11 – 15, was scheduled to see the concrete pour for 28th floor of the Phase tower. In fact, concrete work for the 28th floor had already been rescheduled from the previous week. Weather...