by admin | Jun 1, 2020 | Uncategorized
Home Key milestones for the remainder of spring and summer 2020 at Pier 27. Commercial parking has been consolidated in the north parking lot as of May. Move ins are occurring up to the 20th floor, and 75% occupancy approval was achieved in May. Painting balconies...
by admin | May 25, 2020 | Uncategorized
Municipal Servicing Work Continues in the right of way and on Queens Quay Contractor GFL will be working through this week and into early June to complete the necessary and permitted municipal servicing work. Once GFL has secured the final connections, they will...
by admin | May 19, 2020 | Uncategorized
Municipal Servicing Work Continues this week. Contractor GFL will be working again this week. Last week’s rain on Friday caused them to lose a day, so we expect this will add time to their work schedule this month. GFL is still working on the installation of two...
by admin | May 11, 2020 | Uncategorized
Municipal Servicing Work Continues Contractor GFL is continuing to work on completing municipal service installations. GFL is currently installing two water services in front of the sales centre pavilion. This work will be ongoing for the next 3 weeks until GFL can...
by admin | May 4, 2020 | Uncategorized
Municipal Servicing Work Continues Contractor GFL is continuing to work on completing municipal service installations. This week will see pipe installation work along the right of way on the north side of the site, just south of the existing sidewalk. Work hours this...
by admin | Apr 28, 2020 | Uncategorized
Contractor GFL is completing the remaining municipal service installations starting this week. Work hours will be between 7 a.m. to 5:30 p.m. Monday-Friday. The work program is approximately 4 weeks in duration. It will not impact the Pier 27 access driveway or the...
by admin | Apr 24, 2020 | Uncategorized
Project Update for 15 Queens Quay: Work on the right of way adjacent the Sales Centre is scheduled to be completed by end of day April 24. 15 Queens Quay Project Look Ahead Mechanical penthouse: finishing the exterior by installing metal panels on the corners;...
by admin | Apr 17, 2020 | Uncategorized
Project Update for 15 Queens Quay: Mechanical penthouse – finishing the exterior by installing metal panels on the corners is esitimated to finish by the end of this month (April) 34th floor to the 13th floor – interior finishes as required Hoist suites – 2nd floor to...
by admin | Apr 9, 2020 | Uncategorized
UPDATED April 16, 2020 Focus of work at 15 Queens Quay for the coming week: Balcony railings are being installed on the sections of the balconies that were adjacent the hoist. This work is ongoing for the coming week. Landscaping work is continuing on the site:...
by admin | Apr 6, 2020 | Uncategorized
Per the Province of Ontario’s April 3, 2020 update to the list of essential workplaces, construction work will continue to complete suites and landscaping at 15 Queens Quay East. We will post our next construction update midweek. List of essential workplaces ...