Work this week at the Pier 27 Phase 3 Tower will pick up from last week with more concrete pouring. Work will continue on the ground floor slabs.There will also be work to pour the ground verticals, the walls and columns of that rise from the ground floor.Work will...
by admin | Jan 19, 2018 | Uncategorized
In response to feedback from resident, the construction management team has revised the start time of the necessary power shut down on February 12th. The power will now be shut off in 29 Queens Quay from 8 am to 10 pm. This shut down is necessary to enable the setup...