by admin | Feb 26, 2018 | Uncategorized
This week the focus of work on the Phase 3 tower continues to be concrete pours and related work on the ground floor, mezzanine and 2nd floor levels:Remaining ground floor slab concrete workContinuing ground floor vertical columns to the 2nd floorOngoing mezzanine...
by admin | Feb 20, 2018 | Uncategorized
This week the focus of work on the Phase 3 tower continues to be concrete pours and related work on the ground floor, mezzanine and 2nd floor levels: Ground floor slab Ground floor vertical columns to the 2nd floor Mezzanine vertical columns to the 2nd floor Second...
by admin | Feb 13, 2018 | Uncategorized
Form the 13th through the 16th of February concrete work continues on the ground floor, mezzanine and second levels. Construction crews at the Phase 3 tower will be pouring concrete in the following areas: South mezzanine level Ground floor level Second Level Walls...
by admin | Feb 12, 2018 | Uncategorized
We are pleased to confirm that the power is back on at 29 Queens Quay seven hours ahead of schedule. Hot and cold running water is also fully restored after a short, unexpected but necessary interruption this afternoon. The essential electrical work required to setup...
by admin | Feb 12, 2018 | Uncategorized
Today’s electrical power shut off at 29 Queen’s Quay has entailed an unfortunate and unexpected water shut-off. The development team and the construction managers want to thank everyone for their ongoing patience and co-operation. The good news is that the crews...