Phase 3 construction overview Feb 27 – Mar 2

This week the focus of work on the Phase 3 tower continues to be concrete pours and related work on the ground floor, mezzanine and 2nd floor levels:Remaining ground floor slab concrete workContinuing ground floor vertical columns to the 2nd floorOngoing mezzanine...

Overview of construction work February 20 – 23

This week the focus of work on the Phase 3 tower continues to be concrete pours and related work on the ground floor, mezzanine and 2nd floor levels: Ground floor slab Ground floor vertical columns to the 2nd floor Mezzanine vertical columns to the 2nd floor Second...

Phase 3 Construction work February 13 – 16

Form the 13th through the 16th of February concrete work continues on the ground floor, mezzanine and second levels. Construction crews at the Phase 3 tower will be pouring concrete in the following areas: South mezzanine level Ground floor level Second Level Walls...