Phase 3 Construction Overview Mar 26 – 29, 2018

UPDATE: scheduled to remove and reconstruct a section of concrete slab, at grade level, just west of the entrance to the 29 Queen’s Quay parking garage, was again rescheduled to the following week. 29 Queens Quay Parking Garage. Work continues this week in the...

Phase 3 Construction Overview Mar 19 – 23, 2018

This week work  was scheduled to get underway to remove and reconstruct a section of concrete slab, at grade level, just west of the entrance to the 29 Queen’s Quay parking garage. However, this work is now scheduled to begin next week. Once the existing slab is...

Phase 3 Construction Overview Mar 12 – 16, 2018

This week concrete pours continue for the second and third floors continue; and the first concrete pours for the fourth floor will begin week, such as: Second floor deck pours Monday through Friday. Third floor deck pours Monday and Tuesday. Vertical columns from the...

Phase 3 Construction Overview Mar 5 – 9, 2018

This week concrete pours for the third floor slab are scheduled to begin and continue through the week.  Concrete work will also continue in these areas: Remaining vertical columns from the ground floor to the second floor. Pouring mezzanine vertical columns to the...