This week concrete pours for the third floor slab are scheduled to begin and continue through the week. Concrete work will also continue in these areas:
- Remaining vertical columns from the ground floor to the second floor.
- Pouring mezzanine vertical columns to the 2nd floor.
- Continuing pouring the second floor vertical columns to the 3rd floor.