Phase 3 Construction Overview Mar 12 – 16, 2018

This week concrete pours continue for the second and third floors continue; and the first concrete pours for the fourth floor will begin week, such as: Second floor deck pours Monday through Friday. Third floor deck pours Monday and Tuesday. Vertical columns from the...