Phase 3 Construction overview April 30 – May 4, 2018

This week work on the Phase 3 tower is focussed in three main areas:Work is continuing to remove the concrete slab in the 29 Queens Quay roundabout lane, adjacent to the southeast corner of the podium. Crews will be pouring concrete on floors four and five of the...

Update work in 29 Queens Quay garage

UPDATE – April 24, 2018 Work in the 29 Queens Quay garage will be completed today, April 24, or at the latest tomorrow, April 25. Every effort is being made to ensure the safe and quick and completion of clean-up efforts. If you have any questions about this...

Phase 3 Construction overview April 23 – 27, 2018

Work at 29 Queens Quay This week subcontractors Mayfair will be working on P1 level of the 29 Queens Quay parking garage on Monday and Tuesday. This work will include the clean-up of parking spots. Mayfair will also be working in the generator room next week.  Phase 3...