Work at 29 Queens Quay
This week subcontractors Mayfair will be working on P1 level of the 29 Queens Quay parking garage on Monday and Tuesday. This work will include the clean-up of parking spots.
Mayfair will also be working in the generator room next week.
Phase 3 Tower work
This week work on the Phase 3 tower is focussed in three main areas:
- Work is continuing to remove the concrete slab in the 29 Queens Quay roundabout lane, adjacent to the southeast corner of the podium.
- Pouring concrete on floors four and five of the Phase 3 podium.
- Flying formwork tables to the third and fourth floors. These are the wooden structures used to provide forms into which concrete is poured.