This week work on the Phase 3 tower is focussed in three main areas:

  1. Work is continuing to remove the concrete slab in the 29 Queens Quay roundabout lane, adjacent to the southeast corner of the podium. 
  2. Crews will be pouring concrete on floors four and five of the Phase 3 podium. 
  3. Flying formwork tables to the fourth and fifth floors. These are the wooden structures used to provide forms into which concrete is poured.