Phase 3 Construction overview May 28 – June 1, 2018

Phase 3 Tower This week work on the Phase 3 Tower will see the finishing the 7th floor concrete slab and work on the walls/columns that connect to the 8th floorWork will also begin on the forming of the 8th floor slab at south end of the podium. Wooden forming panels...

Phase 3 Construction overview May 22 – 25, 2018

Phase 3 Tower This week work on the Phase 3 Tower will see the finishing the 6th floor concrete slab and work on the walls/columns that connect to the 7th floorWork will also begin on the forming of the 7th floor slab at south end of the podium. Crews will also remove...

Phase 3 Construction overview May 14 – 18, 2018

Phase 3 Tower This week concrete work will proceed on the 5th and 6th levels of the podium. Both floor slab and vertical columns will be poured on the 5th level and on the the southern portion of the 6th level. Wooden forming panels will be moved up a level as work is...

Phase 3 Construction overview May 7 – 11, 2018

Phase 3 Tower Construction Overview This week concrete work on the tower will progress to the fifth and sixth floors. This will include concrete pours for floor slabs and vertical columns.It is expected that all concrete work will be completed within normal weekday...