Phase 3 Construction overview May 14 – 18, 2018

Phase 3 Tower This week concrete work will proceed on the 5th and 6th levels of the podium. Both floor slab and vertical columns will be poured on the 5th level and on the the southern portion of the 6th level. Wooden forming panels will be moved up a level as work is...