Phase 3 Tower
This week work on the Phase 3 Tower will see the finishing the 7th floor concrete slab and work on the walls/columns that connect to the 8th floor
Work will also begin on the forming of the 8th floor slab at south end of the podium.
Wooden forming panels will removed or be flown into position with the onsite cranes, as concrete work progesses.
Please check back for further updates. If you have questions about the progress of the construction please get in touch with us at contact@pier27construction.info
29 Queens Quay Roundabout
Waterproofing work on the section of the 29 Queens Quay roundabout has been completed. Stone pavers that have been stored on-site are scheduled to begin being put back in place this week.
Is the roundabout completion still on track for completion? There is a significant amount of congestion at 29 QQE phase 1 entrance.