Phase 3 Construction overview June 25 – 29, 2018

Phase 3 Tower Work on the Phase tower has now reached the 10th floor of the podium, another milestone in the construction of the newest addition to Pier 27. This week work will be occurring on multiple floors of the podium as detailed here: Ground Floor: Installing...

June 23 – Saturday site work at Pier 27 Phase 3

Saturday work This Saturday, starting at 9 am, a 2-person crew will be on site working on concrete. There should be no noticeable impact on our neighbours. Our overview for the week of June 25th will be posted by or before 7 am on Monday, June 25. Please note that...

Phase 3 Construction overview June 18 – 22, 2018

Phase 3 Tower This week the 8th floor of the Phase 3 tower will be complete. Forming work on the 9th floor will continue. On Monday there will be a concrete pump in the west parking lot, pouring part of the 9th floor slab. Also this week, a speed fan will be installed...

29 Queens Quay Roundabout Update

29 Queens Quay Roundabout Work on restoration of the 29 Queens Quay Roundabout has been continuing over the past 5 days. The original interlocking pavers, which have been stored, are being put back in place on top of a newly waterproofed concrete under-layer. It is...

Phase 3 Construction overview June 11 – 15, 2018

Phase 3 Tower This week sees another milestone reached as forming for the 9th  floor concrete slab will begin. The 8th floor of concrete work is expected to be completed this week. Work will continue on the west side of ground floor:  excavating and removing tops of...