This week sees another milestone reached as forming for the 9th floor concrete slab will begin.
The 8th floor of concrete work is expected to be completed this week.
Work will continue on the west side of ground floor: excavating and removing tops of steel piles. There will be some additional, unavoidable noise
Note: we will post an update on progress on the 29 Queens Quay roundabout in the afternoon of Tuesday, June 12.
Please check back for further updates. We will post new information here if there are further activities of note. If you have questions about the progress of the construction please get in touch with us at contact@pier27construction.info