Phase 3 Tower


IMG_20180702_230143_827
IMG_20180702_230453_171

Work on the Phase Three tower has now reached the 10th floor of the podium, another milestone in the construction of the newest addition to Pier 27. This week work will be occurring on multiple floors of the podium as detailed here: 

Ground Floor:

  • Installing plumbing and heating.

5th Floor:  

  • Grinding and patching. 
  • Installing drains.

10th Floor 

  • Slab concrete pours get underway throughout the week

29 Queens Quay Roundabout


IMG_20180702_230654_671

While waiting for the delivery of additional pavers that match the existing pavers, crews will be doing additional waterproofing work in the area.

We expect to have an update on work on the roundabout next week. Please check back with us.