Phase 3 Tower
Work on the Phase Three tower has now reached the 10th floor of the podium, another milestone in the construction of the newest addition to Pier 27. This week work will be occurring on multiple floors of the podium as detailed here:
Ground Floor:
- Installing plumbing and heating.
5th Floor:
- Grinding and patching.
- Installing drains.
10th Floor
- Slab concrete pours get underway throughout the week
29 Queens Quay Roundabout
29 Queens Quay Roundabout
29 Queens Quay Roundabout
While waiting for the delivery of additional pavers that match the existing pavers, crews will be doing additional waterproofing work in the area.
We expect to have an update on work on the roundabout next week. Please check back with us.
Please make replacing the round about a higher priority. The residents at 29 QQE have been promised it will be returned to our use in April only to see the delays continue month after month. Everything just takes resources so please invest the appropriate resources to ensure this gets completed soon.
The Developer should be invested in getting this completed too since they can’t be getting much interest in selling the last of their huge units in the building while front looks like such a mess!
Can you remind workers that are using 29 Queens Quay phase 1 underground parking that there is no smoking in common areas, stairwells or elevators.