Concrete pours continue on the 10th floor of the Phase Three tower this week . This week work will be occurring on multiple floors of the podium as detailed here:
Ground Floor:
- Installing plumbing and heating continues.
5th and 6th Floors:
- Grinding and patching.
- Installing drains.
10th Floor
- Slab concrete pours throughout the week
29 Queens Quay Roundabout
29 Queens Quay Roundabout
29 Queens Quay Roundabout
29 Queens Quay Roundabout
Unfortunately the need for further reinforcement and waterproofing of the original slab under the west section of the roundabout will delay completion of this work until the beginning of August.
We now expect the roundabout . Please check back with us next week for more news on the progress of restoring the roundabout.