Phase 3 Tower Concrete pours continue on the 10th floor and move to the 11th floor of the Phase Three tower this week10th floor Pouring vertical columns from the 1oth to 11th floors.11th Floor Slab concrete pours begin and continue throughout the week.Pouring vertical...
by admin | Jul 23, 2018 | Uncategorized
Work in the 29 Queens Quay Parking Garage An element of the construction of the Phase 3 Tower at Pier 27, the Phase 3 underground garage needs to be connected via secure vestibules to the existing 29 Queens Quay garage on levels P1, P2, and P3. This work has been part...