Phase 3 Tower
Phase 3 Tower
Phase 3 Tower
The hoist — external elevator is scheduled to begin being installed on beginning on Tuesday, August 7th. Also this week, concrete pours continue on the 11th floor and are beginning on the 12th floor the Phase Three tower this week
11th Floor
- Slab concrete pours begin and continue throughout the week.
- Pouring vertical columns from the 11th to 12th floors.
12th Floor
- Concrete pours scheduled to begin mid-week on the 12th floor slab.
29 Queens Quay Roundabout
29 Queens Quay Roundabout
29 Queens Quay Roundabout
Work continues on the 29 Queens Quay roundabout with the placement of new pavers. It is expected that the roundabout will be completed by late September.