Phase 3 Tower

20180802_161130
20180802_161325

The hoist — external elevator is scheduled to begin being installed on beginning on Tuesday, August 7th. Also this week, concrete pours continue on the 11th floor and are beginning on the 12th floor the Phase Three tower this week

11th Floor

  • Slab concrete pours begin and continue throughout the week.
  • Pouring vertical columns from the 11th to 12th floors.

12th Floor

  • Concrete pours scheduled to begin mid-week on the 12th floor slab. 

29 Queens Quay Roundabout

20180802_161247
20180802_161257

Work continues on the 29 Queens Quay roundabout with the placement of new pavers. It is expected that the roundabout will be completed by late September.