Phase 3 Construction overview August 20 – 25, 2018

Phase 3 Tower The installation of the hoist — the external construction elevator — continues this week on the east side of the tower. 2nd and 3rd FloorsInstalling windows on the second and third floors through the week. 12th FloorSlab concrete pours to be complete...