The installation of the hoist — the external construction elevator — continues this week on the east side of the tower.
2nd and 3rd Floors
- Installing windows on the second and third floors through the week.
12th Floor
- Slab concrete pours to be complete this week.
- Pouring vertical columns from the 12th to 13th floors.
NOTE:
We expect there will be work on site on Saturday August 25 and will post an update on the specific work later in the week.