Phase 3 Tower


The installation of the hoist — the external construction elevator — continues this week on the east side of the tower. 

2nd and 3rd Floors

  • Installing windows on the second and third floors through the week. 

12th Floor

  • Slab concrete pours to be complete this week.
  • Pouring vertical columns from the 12th to 13th floors.

NOTE:

We expect there will be work on site on Saturday August 25 and will post an update on the specific work later in the week.