Phase 3 Tower

20180824_144716
20180824_144727
20180824_144735

  • The installation of the hoist — the external construction elevator — continues this week on the east side of the tower. 

P1, P2, P3 & P4 Levels

  • Installing block walls
  • HVAC installation

Ground Floor

  • Install Plumbing / Heating

2nd Floor

  • Layout of corridor and mock-up suites
  • Install firestopping/foam vent boxes

3rd Floor

  • Install windows
  • Layout of corridor and mock-up suites

4th Floor

  • Layout of corridor and mock-up suites

12th Floor

  • Waterproof deck beneath pool and planters
  • Infill pool area with insulation
  • Forming the pool slab

13th Floor

  • Slab concrete pour – scheduled for August 31.

NOTES:

  1. We do not expect  work on-site for Saturday September 1 but if this should change we will post an update later in the week. 
  2. If the concrete slab pour scheduled for August 31 has to continue past 7:00 pm, we will post an update later this week.

29 Queens Quay

On Thursday, August 28th  work is required to be done in the P4 generator room from 7:00 A.M to 3:00 P.M.  Electricians will be tying into the shared generator as it is designed to support the Phase 3 tower as well as 29 Queens Quay. 

Property management at 29 Queens Quay has been advised. This work will have no impact on the power supply to 29 Queens Quay.