Phase 3 Tower
- The installation of the hoist — the external construction elevator — continues this week on the east side of the tower.
P1, P2, P3 & P4 Levels
- Installing block walls
- HVAC installation
Ground Floor
- Install Plumbing / Heating
2nd Floor
- Layout of corridor and mock-up suites
- Install firestopping/foam vent boxes
3rd Floor
- Install windows
- Layout of corridor and mock-up suites
4th Floor
- Layout of corridor and mock-up suites
12th Floor
- Waterproof deck beneath pool and planters
- Infill pool area with insulation
- Forming the pool slab
13th Floor
- Slab concrete pour – scheduled for August 31.
NOTES:
- We do not expect work on-site for Saturday September 1 but if this should change we will post an update later in the week.
- If the concrete slab pour scheduled for August 31 has to continue past 7:00 pm, we will post an update later this week.
29 Queens Quay
On Thursday, August 28th work is required to be done in the P4 generator room from 7:00 A.M to 3:00 P.M. Electricians will be tying into the shared generator as it is designed to support the Phase 3 tower as well as 29 Queens Quay.
Property management at 29 Queens Quay has been advised. This work will have no impact on the power supply to 29 Queens Quay.