by admin | Sep 28, 2018 | Uncategorized
Work on site Saturday from 9 AM There will be work this Saturday, September 22, at Pier 27 Phase 3 from 9 AM till the early afternoon. Types of work will include:GrindingWindow installationGeneral site housekeepingOur overview of next week’s schedule will be posted by...
by admin | Sep 24, 2018 | Uncategorized
Phase 3 Tower overview for the week This week work will reach the 16th floor of the Phase 3 tower. A mix of internal and external work will occur on the lower floors, with concrete work focussed on the 15th and 16th floors. We will update this site later in the week...
by admin | Sep 21, 2018 | Uncategorized
Work on site today from 9 AM There will be work this Saturday, September 22, at Pier 27 Phase 3 from 9 AM till the early afternoon. Types of work will include:GrindingWindow installationGeneral site housekeepingOur overview of next week’s schedule will be posted by or...
by admin | Sep 20, 2018 | Uncategorized
Friday’s concrete pour may run till 11 pm We expect Friday’s scheduled concrete pour will continue into the evening, possibly as late as 11 pm. As we note on this site (please click here), continuous concrete pours, which include the pouring and the finishing of...
by admin | Sep 17, 2018 | Uncategorized
Phase 3 Tower overview for the week Ground FloorInstall Plumbing / Heating14th FloorVertical columns from 14th to 15th floor15th FloorSlab Pour Concrete Pours this week As we note on this site (please click here), continuous concrete pours, which include the pouring...