Phase 3 Construction overview September 4 – 7, 2018

Phase 3 Tower The installation of the hoist — the external construction elevator — continues this week on the east side of the tower. P1, P2, P3 & P4 LevelsHVAC installation continuesGround FloorInstall Plumbing / Heating3rd FloorInstall windowsLayout of corridor...