Phase 3 Tower

20180824_144735
20180824_144727
20180824_144748

  • The installation of the hoist — the external construction elevator — continues this week on the east side of the tower. 

P1, P2, P3 & P4 Levels

  • HVAC installation continues

Ground Floor

  • Install Plumbing / Heating

3rd Floor

  • Install windows
  • Layout of corridor and mock-up suites
  • Install firestopping/foam vent boxes

4th Floor

  • Install windows

12th Floor

  • Forming the pool slab
  • Pouring the pool slab

13th Floor

  • Stressing the 13th floor slab
  • Vertical columns from the 13th to 14th floors