Work on site Saturday from 9 AM

There will be work this Saturday, September 22, at Pier 27 Phase 3 from 9 AM till the early afternoon. Types of work will include:

  • Grinding
  • Window installation
  • General site housekeeping

Our overview of next week’s schedule will be posted by or before 7 am, Monday, October 1.

Concrete Pour, Monday October 1

The 16th floor slab concrete pour is scheduled for Monday, October 1st. Pouring and finishing work is expected to go late.

Finishing for 15th floor pour on September 21st went through the night due to weather conditions. It is hoped that Monday’s scheduled concrete work will be completed no later than 11 pm but we will post an update on Monday is there is new information.