19th Floor Concrete Pour – Monday October 29, 2018

Concrete pour all day Concrete pump The main slab concrete pour for the 19th floor is scheduled for this Monday, October 29. This pour and subsequent pours will be using the concrete pump that is located just east of the Phase 3 tower. Concrete is pumped through a...

Pier 27 – Saturday work, October 27, 2018

Work on site Saturday from 9 AM There will be work on site at the Pier 27 Phase 3 tower from 9 am. Crews will be working on:Window installationBalcony railing installation Framing interiorsGeneral site housekeepingUPDATED REMINDER: the 19th floor slab concrete pour is...

South crane coming down today at Pier 27

UPDATE October 24, 2018 Originally scheduled for November, the south crane is being dismantled and removed today. This is the crane located closest to 29 Queens Quay East.  The crane removal contractors had an unexpected availability so Pier 27 Phase 3 construction...

Phase 3 Construction overview October 22 – 27, 2018

Phase 3 Tower overview for the week Concrete being lifted to the 18th floor This week concrete work for the 19th floor will get underway.  However, at this time we the major concrete slab pour for the 19th floor is not expected until Monday, October 29. If this...