by admin | Oct 30, 2018 | Uncategorized
Phase 3 Tower overview for the balance of the week For the balance of this week, October 30 – November 3, exterior work will focus on pouring vertical columns from the 19th to the 20th floor and preparing for next week’s 20th floor slab pour. As with this...
by admin | Oct 28, 2018 | Uncategorized
Concrete pour all day Concrete pump The main slab concrete pour for the 19th floor is scheduled for this Monday, October 29. This pour and subsequent pours will be using the concrete pump that is located just east of the Phase 3 tower. Concrete is pumped through a...
by admin | Oct 26, 2018 | Uncategorized
Work on site Saturday from 9 AM There will be work on site at the Pier 27 Phase 3 tower from 9 am. Crews will be working on:Window installationBalcony railing installation Framing interiorsGeneral site housekeepingUPDATED REMINDER: the 19th floor slab concrete pour is...
by admin | Oct 24, 2018 | Uncategorized
UPDATE October 24, 2018 Originally scheduled for November, the south crane is being dismantled and removed today. This is the crane located closest to 29 Queens Quay East. The crane removal contractors had an unexpected availability so Pier 27 Phase 3 construction...
by admin | Oct 21, 2018 | Uncategorized
Phase 3 Tower overview for the week Concrete being lifted to the 18th floor This week concrete work for the 19th floor will get underway. However, at this time we the major concrete slab pour for the 19th floor is not expected until Monday, October 29. If this...