Work on site Saturday from 9 AM

There will be work this Saturday, Saturday October 13, at Pier 27 Phase 3 from 9 AM till the early afternoon. Types of work will include:

  • Grinding
  • Window installation
  • Form cracking–i.e. separating wooden forms to prepare them for use in next week’s concrete work.
  • General site housekeeping

Our overview of next week’s schedule will be posted by or before 7 am, Monday, October 15.