Work on site Saturday from 9 AM
There will be work on site at the Pier 27 Phase 3 tower from 9 am.
Crews will be working on:
- Window installation
- Balcony railing installation
- Framing interiors
- General site housekeeping
UPDATED REMINDER: the 19th floor slab concrete pour is scheduled for Monday, October 29. This will run all day and into the evening.
We will post a detailed look at Monday’s concrete pour prior to 7 am Monday, October 29. Our full overview of the balance of the week’s schedule will be posted by or before 7 am, Tuesday, October 30.