Phase 3 Tower overview for the balance of
the week
Phase 3 Tower overview for the balance of
the week
Phase 3 Tower overview for the balance of
the week
Phase 3 Tower overview for the balance of
the week
For the balance of this week, October 30 – November 3, exterior work will focus on pouring vertical columns from the 19th to the 20th floor and preparing for next week’s 20th floor slab pour. As with this past Monday’s 19th floor slab pour, the concrete pump will be used to transport concrete up to the 19th level.
Interior work on the podium level floors is focussed installing electrical systems, framing, initial drywall and beginning for create individual suites.
Detail of tower work this week
Detail of tower work this week
Podium Level Floors
- Work on stairwells, shafts and electrical closets
- General electrical work
- Installing risers and garbage chutes
- Drywall
- Unit layout and framing
19th Floor
- Vertical column pours from the 19th to 20th floors
- Preparing for the slab pour on the 20th floor
Saturday work on November 3
- We will provide details on Saturday’s planned work later in the week.