Work on site at Pier 27 from 9 am

20181130_150032
20181130_150253

There will be crews on site at the Pier 27 Phase 3 Tower from 9 am this Saturday. They will be working on:

  • Framing walls on the podium levels of the tower
  • Installing windows
  • General site housekeeping 

Our overview of construction for the week of December 3 – 8, will be posted by or before 7 am Monday, December 3.