Work on site at Pier 27 from 9 am


There will be crews on site at the Pier 27 Phase 3 Tower from 9 am this Saturday. They will be working on:

  • Window installers on site – 15th floor
  • Third floor suite framing
  • Miscellaneous cleaning

Our overview of construction for the week of December 17 – 21, will be posted by or before 7 am Monday, December 17