by admin | Jan 28, 2019 | Uncategorized
One-hour power shut down – 29 & 39 Queens Quay + Phase 3, February 6, 2019. Please note that due to the extreme cold today’s (January 31) planned power shutdown across Pier 27 has been rescheduled to Wednesday, February 6 from 2:30 pm to 3:30 pm....
by admin | Jan 28, 2019 | Uncategorized
UPDATED: Phase 3 Construction Overview The planned one-hour shutdown of the main transformer at Pier 27 for Thursday, January 31 from 2 pm to 3 pm, was rescheduled to Wednesday, February 6 – please click here for details. This week’s construction focus at...
by admin | Jan 25, 2019 | Uncategorized
Saturday work on site at Pier 27 There will be large crane and concrete work on site on Saturday, January 26 from 9 am. The recent weather has continued to complicate construction. Regular concrete pours are taking longer given the extreme and variable temperatures....
by admin | Jan 21, 2019 | Uncategorized
UDATED Jan 21/19 Phase 3 Tower overview for the week. This week’s scheduled to major 26th floor concrete pour has been rescheduled from today, Monday’s 26th, to Tuesday, January 22nd due to the extreme cold and windchill values. As we noted before, work...
by admin | Jan 14, 2019 | Uncategorized
UPDATED – Phase 3 Tower overview for the week This week work at the Pier 27 Phase 3 tower will begin on forming and pouring columns rising from the 25th floor to the 26th floor. Large crane work will involve flying the forming tables to the top of the tower and...