Phase 3 Tower overview for the week
Phase 3 Tower overview for the week
This week concrete work resumes at the Pier 27 Phase 3 tower.
This will include using the crane to fly forming tables for the 25th floor.
A major concrete pour is scheduled for Friday, January 11th.
Window installation will get underway on the 16th floor.
Interior work on the podium levels will ongoing through the week.
We will provide an update later this week with further details and more information on the planned work for Saturday.