by admin | Feb 27, 2019 | Uncategorized
Wednesday Feb 27 recap Given the snowstorm today, February 27, concrete work as suspended. Drywall, electrical work, floor levelling and framing continued in the podium and lower tower levels. Work for the balance of the week With mostly clear skies forecast for...
by admin | Feb 22, 2019 | Uncategorized
UPDATED: for the Week of February 25, 2019 A key focus at the beginning of the week will be preparing for the next major slab concrete pour, which has now been rescheduled for Monday, March 4, as a result of the delay caused by the snow storm on Wednesday, February...
by admin | Feb 20, 2019 | Uncategorized
Thursday Electrical Room Work 29 Queens Quay E. Tomorrow, Thursday, February 21, from 7:00 AM to 2:00 PM, TMG’s electricians will be accessing 29 Queens Quay, Parking Level 4 (P4), Generator Room. The generator is shared between Phase 3 building and 29 Queens...
by admin | Feb 15, 2019 | Uncategorized
Recap for the week of Feb 11 – 15, 2019 This past week, February 11 – 15, was scheduled to see the concrete pour for 28th floor of the Phase tower. In fact, concrete work for the 28th floor had already been rescheduled from the previous week. Weather...
by admin | Feb 11, 2019 | Uncategorized
Phase 3 Construction Overview This week’s major construction activity will be focussed on preparing for the 28th floor concrete slab pour. On Monday and Tuesday forming tables will be flown up to the top of the tower in preparation for the concrete work. The...