Work on-site from 9 am at Phase 3

20190201_142142
20190201_142555
20190201_141950

There will work on-site at Phase 3 this Saturday from 9 am onwards. 

Work will occur on the exterior of the building, including:

  • Railing installation
  • Window installation 

Interior work will focus on:

  • Framing
  • Levelling floors
  • Drywall installation.

Our construction overview for next week will be posted by or before 7 am, Monday, February 11.