Phase 3 Construction Overview

IMG_20190211_002230_489
IMG_20190211_002109_359

This week’s major construction activity will be focussed on preparing for the 28th floor concrete slab pour. 

On Monday and Tuesday forming tables will be flown up to the top of the tower in preparation for the concrete work. 

The major concrete pour is scheduled for this Friday, February 15, pouring occurring in the morning and early afternoon; concrete finishing running from the mid-afternoon through the evening. 

However, given the forecast for Tuesday, February 12, the schedule may be subject to change. We will update this post during the week as may be required.  Please check back for updates. 


Interior & Exterior work at Phase 3

Exterior

Throughout the week work will continue on the railings, windows and balconies, weather permitting. 

Interior

Inside the podium, work proceeds throughout on suite layouts, framing units, levelling suite floors, installing drywall and pluming infrastructure. 

Saturday

We expect a full day of interior and exterior work on Saturday, February 16 but we will post specific information on Saturday work on Friday or as soon as we have the information available.