Week recap, Saturday construction & Look Ahead, February 16/19 +

by admin | Feb 15, 2019 | Uncategorized

Recap for the week of Feb 11 – 15, 2019 This past week, February 11 – 15, was scheduled to see the concrete pour for 28th floor of the Phase tower. In fact, concrete work for the 28th floor had already been rescheduled from the previous week. Weather...

Find Us

Address – Site Developers
56 The Esplanade #308, Toronto, ON M5E 1A7

About This Site

This site provided construction information for Cityzen Development Group & Fernbrook Homes’ Pier 27 15 Queens Quay from January 2018 through May 2020.

Search

February 2019
M T W T F S S
 123
45678910
11121314151617
18192021222324
25262728  
« Jan   Mar »
  • Facebook
  • Twitter
  • Google
  • Instagram
  • RSS

Designed by Elegant Themes | Powered by WordPress