UPDATED: for the Week of February 25, 2019
A key focus at the beginning of the week will be preparing for the next major slab concrete pour, which has now been rescheduled for Monday, March 4, as a result of the delay caused by the snow storm on Wednesday, February 27.
Forms will be flown by the crane to the 28th floor for columns and slab sections. Columns from the 28th to the 29th floor will be formed and poured.
Work on the interiors will continue in the podium levels and will move into the tower floors.
There will be concrete trucks and deliveries accessing the site.
Our next update will be posted on Wednesday, February 27.
Electrical work in the 29 Queens Quay Generator Room
This Tuesday, February 26, from 7:00 AM to 2:00 PM, TMG’s electricians will once again be accessing the 29 Queens Quay E., Parking Level 4 (P4), Generator Room. The generator is a shared service between Phase 3 building and 29 Queens Quay East.
As part of the ongoing work required to complete Phase 3, electricians will be finishing the connection of electrical cables to the P4 generator, from the Phase 3 side of the site.
As per the work that was conducted on Thursday, February 21, there should be no disruption to services at 29 Queens Quay East. Property managers have been advised.
Saturday February 23
There will work on-site at Phase 3 this Saturday from 9 am onwards.
Crews will be ensuring the site is secure for the forecast strong winds that are expected to occur on Sunday, February, 24.
Similarly to last week, exterior work will also include:
- Railing installation, and
- Window installation.
And, interior work will focus on:
- Framing,
- Levelling floors,
- Drywall installation, and
- Electrical work.