4-day Lookahead at Pier 27 Phase 3

20190301_141513
20190301_141724
20190301_141902

Construction highlights in the coming 4 days:

Crews will continue to raise the hoist: the external elevator for Phase 3. 

There will be concrete pours on Friday for walls and columns from the 29th to 30th floors.

Installing railings on 9th and 10th floors.

Installing windows on 21st floor.

Continuing work on the interiors: framing 9th floor suites; boarding 6th floor suites. There will be deliveries of materials to the site to support this work.  

Saturday

General housekeeping work on site. 

Opening wall forms on the 29th floor starting at 9 AM.

Installing railings. 

Interior work on the podium suites.