Phase 3 overview
As of today, the next major concrete pour for the 30th floor is scheduled for this coming Friday, March 15th. As with previous major slab concrete pours it is expected to run throughout the day, with concrete finishing running into the evening.
As the weather forecast for this week is for considerably milder weather, we do not expect weather-delays to affect the schedule.
In preparation for Friday’s slab pour, work will continue this week on completing wall and column pours from the 29th to the 30th floors. Forming tables will also be flown up to the top of the building with the large crane.
Work will continue on the interiors with suite layout work, drywall, electrical and floor levelling.
We will post a mid-week update on Wednesday March 13. Please check back for updates.