Pier 27 Construction Overview for the week of March 18

Pier 27 Construction Overview for the week of March 18

Phase 3 Construction overview This week the focus of work on the top of the Phase 3 Tower will be prepping, forming and pouring columns and walls from the 30th to the 31st floor.  We expect the 31st floor slab to be poured on Monday, March 25th. If the schedule for...