Phase 3 Construction overview


This week the focus of work on the top of the Phase 3 Tower will be prepping, forming and pouring columns and walls from the 30th to the 31st floor.
We expect the 31st floor slab to be poured on Monday, March 25th. If the schedule for this next major slab pour changes we will provide details in our mid-week update on Wednesday afternoon.

Exterior work will continue through the week on windows and railings. Window installation is close to complete on the north and west faces of the ground floor retail level.
The hoist (external elevator) will continue being raised to the 26th floor level.