Midweek Update
Work continues at Pier 27 Phase 3 through the end of the week to prepare for the next major slab pour on the 32nd floor and is expected next week. Columns and walls running from the 31st floor to the 32nd will be formed and poured.
Deliveries to the site will continue, bringing material and supplies for the interior work that is continuing from the 2nd floor through the 26th floor.
Saturday Work March 30
Crews will be on site from 9 am.
General housekeeping work on site.
Interior drywall and suite work.
Installing railings.
Installing windows.
NOTE: Our next update will be posted by or before 7 am Monday, April 1.