by admin | Apr 29, 2019 | Uncategorized
This week’s major slab pour is scheduled for Friday May 3 for the 35th floor. This is the final major slab pour prior to the mechanical penthouse levels. Please note that deliveries to the site are ongoing through the week. Suites are being framed and...
by admin | Apr 23, 2019 | Uncategorized
Midweek Update The 34th floor concrete pour was successfully completed today, April 23. Finishing work on the slab will continue into the evening. The next major slab pour is expected to occur on Friday May 3 for the 35th floor. Deliveries to the site are ongoing,...
by admin | Apr 18, 2019 | Uncategorized
Construction Update The concrete 34th floor slab pour that was scheduled for today has been postponed to Tuesday, April 23. It will begin at 7 am. Concrete will be poured through the afternoon. Concrete finishing will continue into the evening, possibly as late as 10...
by admin | Apr 15, 2019 | Uncategorized
This week’s major concrete pour for the 34th floor slab is scheduled for Thursday, April 18, starting at 7:00 AM. Concrete pouring will continue through the afternoon and concrete finishing will continue into the evening, possibly as late as 10 pm. Window...
by admin | Apr 10, 2019 | Uncategorized
Midweek Update Work continues at Pier 27 Phase 3 through the end of the week and into next week prepare for the next major slab pour on the 34th floor. Columns and walls running from the 33rd floor to the 34th will be formed and poured. Deliveries to the site will...