This week’s major concrete pour for the 32nd floor slab  is scheduled for Tuesday, April 2, starting at 7:30 AM. Concrete pouring will continue through the afternoon and concrete finishing will continue into the evening. 

Window installation is ongoing through the week for the 23rd floor and above. 

Railing installation is ongoing from 10 to 12th floors this week. 

Interior work is on-going: including drywall, suite layouts, framing walls, levelling suite floors and kitchen and bathroom installation.

We will post a midweek update on Wednesday afternoon, April 3. 