Midweek Update
Work continues at Pier 27 Phase 3 through the end of the week to prepare for the next major slab pour on the 33rd floor that is scheduled for Wednesday, April 10. Columns and walls running from the 32nd floor to the 33rd floor will be formed and poured.
Deliveries to the site will continue, bringing material and supplies for the interior work that is continuing from the 2nd floor through the 26th floor. Kitchens continue to installed and laundry equipment is beginning to be installed on the 2nd floor. Suites are being framed and drywalled. Railing installation continues from the 12th to 13th floors and window installation continues from the 24th floor.
Saturday Work April 6
Crews will be on site from 9 am.
General housekeeping work on site.
Interior drywall and suite work.
Installing railings.
Installing windows.
NOTE: Our next update will be posted by or before 7 am Monday, April 8.