Midweek Update

Work continues at Pier 27 Phase 3 through the end of the week and into next week prepare for the next major slab pour on the 34th floor. Columns and walls running from the 33rd floor to the 34th will be formed and poured. 

Deliveries to the site will continue, bringing material and supplies for the interior work that is continuing from the 2nd floor through the 26th floor. Kitchens continue to installed on the 2nd and 3rd floors, and laundry equipment is beginning to be installed on the 2nd floor. Suites are being framed and drywalled. Railing installation and window installation is ongoing. The glazing and exterior walls are completed on the amenity level at the southern end of the top podium floor. 

Saturday Work April 13

Crews will be on site from 9 am.

General housekeeping work on site. 

Interior drywall and suite work.

Installing railings. 

Installing windows.

NOTE: Our next update will be posted by or before 7 am Monday, April 15.