Construction Update
The concrete 34th floor slab pour that was scheduled for today has been postponed to Tuesday, April 23. It will begin at 7 am. Concrete will be poured through the afternoon. Concrete finishing will continue into the evening, possibly as late as 10 pm, to ensure the concrete is set and finished to safety standards.
Looking Ahead
Kitchens and bathrooms continue to be installed on the 2nd, 3rd, 4th floors. Laundry unites are being installed on the 2nd floor. Suites are being framed and drywalled throughout the podium levels.
Railing installation is complete to the 13th floor. Window installation is ongoing from the 26th floor and above. The glazing and exterior walls are nearly completed on the main floor retail level.
The hoist (external construction elevator) will be raised next week to service the tower floors above the 26th storey.


Site Closed Friday, April 19
There will be no work on site tomorrow, Friday, April 19, for the Good Friday statutory holiday.
Saturday Work, April 20
Crews will be on site from 9 am.
General housekeeping and clean-up work on site.
Installing railings above the 13th floor.
NOTE: Our next update will be posted Tuesday afternoon, April 23.