by admin | May 27, 2019 | Uncategorized
This week at Pier 27 crews will be pouring the mezzanine level of the mechanical room on Wednesday, May 29. Other exterior work continues through the week: Installing windows on the 29th floor and above. Railing installation on the 16th floor and above. Interior...
by admin | May 24, 2019 | Uncategorized
Saturday Work May 25 Crews will be on site from 9 am. They will be focussed on: General housekeeping work on site. Interior drywall and suite finishig work. NOTE: Our next update will be posted on Monday, May...
by admin | May 21, 2019 | Uncategorized
This week at Pier 27 work will continue on the mechanical penthouse levels above the 35th floor. There will be ongoing forming and concrete work. There will be deliveries to the site are through the week. Suites are being framed and drywalled from the podium levels...
by admin | May 15, 2019 | Uncategorized
Pier 27 Midweek Update, May 15, 2019 Concrete work continues on the rooftop level as columns and walls are being formed and poured for the mechanical penthouse levels. There are two slab floors to be poured for the two-level mechanical penthouse. Work at the rooftop...
by admin | May 13, 2019 | Uncategorized
Pier 27 Construction Overview Week of May 13, 2019 Concrete work this week will focus on: Pouring walls for the mechanical levels Edges (curbs) for the roof level. Interior work will focus on: Continuing with framing and preparing for drywall on the 20th to 26th...