Construction overview for the week of May 27, 2019

Construction overview for the week of May 27, 2019

This week at Pier 27 crews will be pouring the mezzanine level of the mechanical room on Wednesday, May 29. Other exterior work continues through the week: Installing windows on the 29th floor and above. Railing installation on the 16th floor and above.  Interior...
Midweek Update for Pier 27 Phase 3

Midweek Update for Pier 27 Phase 3

Pier 27 Midweek Update, May 15, 2019 Concrete work continues on the rooftop level as columns and walls are being formed and poured for the mechanical penthouse levels. There are two slab floors to be poured for the two-level mechanical penthouse. Work at the rooftop...
Saturday housekeeping work on-site at Pier 27

Pier 27 Construction Overview, May 13, 2019

Pier 27 Construction Overview Week of May 13, 2019 Concrete work this week will focus on: Pouring walls for the mechanical levels Edges (curbs) for the roof level. Interior work will focus on: Continuing with framing and preparing for drywall on the 20th to 26th...