Midweek Update

The 35th floor concrete pour that was scheduled for Friday May 3 will now take place on Tuesday May 7.

Deliveries to the site are ongoing, bringing material and supplies for the interior work that is continuing from the 2nd floor through the 30th floor. Kitchens continue to installed and laundry equipment is beginning to be installed on the 2nd, 3rd  and 4th floors. Suites are being framed and drywalled, with drywall work now reaching the 19th floor and above.

Railing installation continues from the 14th floor and above. Window installation continues from the 27th floor and above. 

A note on the the recent Pier 27 Phase 3 alarm

There was an electrical malfunction from a hoist speaker that caused the alarm to sound this past weekend. The construction managers regret the inconvenience. After investigating the situation they have been told that this a rare incident that should not repeat in the normal course of work. Should there by any future abnormities during a Sunday or after hours, security dispatch can be reached at 416 218 3226 and they will contact the site security to address the issue.

Saturday Work May 4

Crews will be on site from 9 am.

General housekeeping work on site. 

Interior drywall and suite work.

Installing railings. 

Installing windows.

NOTE: Our next update will be posted on Monday, May 6.